Industrial hall, Iași — 8,000 m² 3D scan for equipment installation

Laser scanning and 3D modelling in a working hall with intermediate steel platforms, to fit new equipment among the existing machinery.

The situation

The client had to bring new equipment in among the machines already in the hall. For that, the designers needed the real geometry: column positions, intermediate platform levels, free clearances and access routes. A few centimetres of difference between plan and reality only shows once the equipment is on the floor.

Why two days on site

The interior complexity set the duration: intermediate steel platforms on several levels, stairs, support structures and equipment in operation. We scanned with a Riegl VZ-400i from enough stations to cover the hidden areas between the platforms, without stopping activity in the hall.

What we delivered

From the point cloud we produced the 3D model of the hall and its platforms, the ground floor plan and cross sections. The model was used to position the new equipment among the existing machines before installation, so clashes appeared on screen, not on site.

The integration of the new equipment was designed by a team of architects from Norway, who worked directly on the 3D model and drawings we delivered.

Project gallery

From the point cloud to the model and drawings. Click an image to enlarge.

Industrial hall, Iași — Sectioned 3D model — the hall structure, platforms and stairs
Sectioned 3D model — the hall structure, platforms and stairs
Industrial hall, Iași — Point cloud — exterior of the hall
Point cloud — exterior of the hall
Industrial hall, Iași — Point cloud — interior, steel structures and equipment in operation
Point cloud — interior, steel structures and equipment in operation
Industrial hall, Iași — BIM model — overall view
BIM model — overall view
Industrial hall, Iași — BIM model — intermediate steel platforms
BIM model — intermediate steel platforms
Industrial hall, Iași — Ground floor plan — survey from the scan
Ground floor plan — survey from the scan
Industrial hall, Iași — Cross sections ST1 and ST2
Cross sections ST1 and ST2
Industrial hall, Iași — Cross sections ST3 and ST4
Cross sections ST3 and ST4

Have a hall to upgrade?

Tell us what equipment you want to integrate. We tell you what we measure, what we deliver and how long it takes. Indicative ranges on the pricing page.

Describe your project →

← All projects · Industrial projects